The process

A fixed completion date, and every phase that gets you there.

Your completion date is agreed before we start, not estimated as we go. We run the same sequence on every job, with the same team, and we write to you every Friday to say where we are against it. Below is the whole build, phase by phase.

Loft Conversion Specialists of the YearWales Prestige Awards 2026/27
  1. Phase 1

    Rip out, steels and new joists

    The loft is cleared, the old ceiling joists are assessed, and the steels go in to carry the new floor. Everything comes in through the loft hatch, so your landing is protected and your roof stays shut.

    Cleared loft with bare timber trusses, a block gable wall and work lights, before conversion
  2. Phase 2

    Structure signed off, floor down

    Building control inspects the steels and joists before anything covers them. Once it is signed off the new floor goes down, and for the first time the space reads as a room.

    New timber joists laid across a steel beam in a loft, ready for the floor deck
  3. Phase 3

    Everything gets ready before we touch the roof

    Windows ordered and delivered, the staircase measured and made, materials on site, trades booked to the day. This is the quiet stretch that means the roof is only ever worked on with everything ready and waiting.

    Loft floor decked out beneath the existing rafters, with materials stacked ready
  4. Phase 4

    The new roof structure, weathertight the same day

    The new roof structure goes in and the openings are formed, and every one of them is made watertight before we walk off it. Your house is never left open, which is the reason nothing happens up here until everything else is ready and waiting.

    New roof lining and insulation boards fitted between rafters with a roof window installed
  5. Phase 5

    First fix, wiring, plumbing, insulation

    Sockets, lighting, heating and any en suite drainage go in, then the insulation. We walk the room with you before it is boarded, because moving a socket now costs nothing.

    Loft at first fix stage with cabling run and plasterboard stacked ready
  6. Phase 6

    Plasterboard, and the staircase goes in

    The one genuinely disruptive stretch downstairs, because the new stair has to break through the existing landing. It is boarded, sheeted and cleaned every evening.

    New timber staircase installed up to the loft before finishing
  7. Phase 7

    Plaster, flooring, second fix

    Skimmed, dried, floored. Doors hung, sockets and switches on, radiators live. The room stops being a build and starts being part of the house.

    Freshly plastered loft walls drying out, with the roof window in place
  8. Phase 8

    Decoration and the en suite

    Painted throughout, tiling and sanitaryware in if you have gone for an en suite, and the staircase finished to match the rest of the house rather than looking bolted on.

    Engineered oak flooring being laid in the finished loft room
  9. Phase 9

    Snagging, sign off, keys back

    Final building control inspection and completion certificate, a walk round with you and a written snag list closed out. Then we are gone, the skip is gone, and the house is yours again.

    The finished loft bedroom with oak flooring, white walls and a roof window

A written update every Friday

What was done this week, what is happening next week, and anything that has changed. You never have to chase us to find out where you are.

The same faces, every day

One team from the first steel to the last coat of paint. Nobody unfamiliar turns up at your door, and nothing gets dropped between trades.

The date is fixed before we start

It goes in the proposal with the price, and the weekly timeline tracks against it. If something behind the plaster genuinely changes it, you hear that from us first and in writing, not on the day.

What people ask about the timeline

How long does a loft conversion take?

Your completion date is agreed before we start and written into the proposal. Ten phases is the typical programme behind it, from first steel to keys back, and a bigger job carries a longer one. Weather, building control and a structure that turns out to be different behind the plaster can still move a date, and if it moves you hear it from us first, in writing.

Can we stay in the house during the work?

Yes, and most people do. For the first four phases the roof is not opened at all, so the bedrooms and the bathroom below stay in normal use. Week seven, when the new stair breaks through the existing landing, is the one genuinely disruptive week, and it is boarded, sheeted and cleaned every evening.

When does the roof actually open?

Week five, and it closes again the same week. Everything, the windows, the staircase, the materials and the trades, is on site and booked before a single tile comes off. That is deliberate, and it is the reason the roof never sits open waiting for a delivery.

How will I know what is happening?

You get a written update every Friday: what was done this week, what is happening next week, and anything that has changed. There is also a payment schedule tied to completed stages, so you can always see where your budget stands.

Want your dates in the diary?

Form, phone consultation, one appointment at the house, then your itemised proposal. That is the whole process before anyone lifts a tile.